Cloud Native · 5 min read

A migration plan that survives cutover day

Most migration risk is decided long before the weekend you move. Here is what to agree up front.

Current estateAWS · Google CloudLANDING ZONEApp serversApp serversDatabasesDatabasesBatch jobsBatch jobsMigration wavesCutover · rollback ready

Start with acceptance, not architecture

Before choosing services, agree per workload what “moved” means: the downtime it can tolerate, the checks that prove it works and who signs it off. Without this, cutover becomes a debate under pressure.

Move in waves you can reverse

Group workloads by dependency and risk. Stateless services go first because they are easy to roll back; stateful systems follow once replication and rollback have been rehearsed. Every wave should have a tested way back.

Rehearse the boring parts

DNS changes, certificate renewals, secrets and connection strings cause more cutover failures than the platform itself. Script them, rehearse them and keep the runbook next to the people who will run it.

Hand over a platform, not a project

The migration is finished when the team that runs the system can deploy, observe and recover it without help. Budget time for templates, dashboards and runbooks as part of the scope, not after it.